Mr Justice Jackson, Technology and Construction
Court
21 December 2004
In considering the question of whether an
employer is entitled to set off liquidated damages against monies
payable to a contractor under an adjudicator's award, the court
must consider the adjudicator's decision: where it followed
from an adjudicator's decision that the employer is entitled to
recover a specified sum of money by way of LADs, then the employer
could set that off against the sums payable to the contractor as a
result of the adjudicator's decision; however, where the
entitlement to LADs has not been determined, either expressly or
impliedly by the adjudicator, then the question of the employer's
entitlement to set off depends upon the terms of the contract and
the facts.
The Defendant (Serco) contracted with the Claimant
(Balfour Beatty) to design, supply, install and test variable
message signs on motorways throughout England. The work was
commenced in March 2001 with completion due on 24th
March 2004. Various events delayed the work. In
particular, delays were caused by the Secretary of State's decision
to implement the procedure for environmental impact assessments
under the Highways Act 1980.
In October 2003 Balfour Beatty claimed a 29 week
extension of time attributable to the delays caused by the
Secretary of State in connection with the environmental impact
assessments. Later, in March 2004 it claimed a longer period,
encompassing not only the October 2003 claim but further claims for
extension of time and loss and expense.
Part of the claim was settled by a claims
management committee in accordance with the contract, but a large
part of the claim remained unsettled and was referred to
adjudication. The adjudicator allowed Balfour Beatty's
extension of time claim and extended the completion date to
7th June 2004, directing that Serco should pay £620,664
plus VAT. Serco refused to pay on the basis that practical
completion had not yet been achieved and since the adjudicator had
only extended time until 7th June 2004, Serco was
entitled to liquidated and ascertained damages (LADs) for the
period after 7th June 2004. It followed that,
since it was entitled to set off the LADs against the sums awarded
by the adjudicator, and since the LADs would exceed the sum payable
under the adjudicator's decision, it owed nothing to Balfour
Beatty.
Balfour Beatty applied for summary judgment to
enforce the adjudicator's decision. Serco argued that the
claim should be dismissed, or at least stayed so that the question
of LADs could be referred back to the adjudicator.
The Court heard detailed arguments about what
claims had been referred to the adjudicator and what the
adjudicator had decided. Balfour Beatty claimed that the
adjudicator had not been asked to consider an extension of time
beyond 7th June and so it could not be argued that he
had refused to grant an extension beyond the 7th June
2004. Serco argued that the adjudicator had positively
refused any extension of time beyond the 7th June 2004
and that it followed that they were entitled to LADs following that
date.
The Court analysed the claim documents and the
adjudicator's decision and found that the adjudicator was leaving
open the question of what further extensions beyond 7th
June 2004 may be due to Balfour Beatty. The Judge considered
that Balfour Beatty's primary case was for an extension to
29th February (although the door was left ajar for the
adjudicator to award a shorter or a longer period if he saw fit to
do so) and whatever it had said about delays after that date could
not have been its entire case on extensions of time after that date
so it would have been unfair for the adjudicator to shut out the
possibility of further extensions being provided. Further,
the Judge concluded that the adjudicator had clearly indicated that
an extension beyond 7th June 2004 was due.
The Judge summarised the case law on the question
of set off against monies payable under an adjudicator's
award. He stated that where it follows from an adjudicator's
decision that the employer is entitled to recover a specified sum
of money by way of LADs, then the employer could set that off
against the sums payable to the contractor as a result of the
adjudicator's decision (provided proper notice is given).
However, where the entitlement to LADs has not been determined,
either expressly or impliedly by the adjudicator, then the question
of the employer's entitlement to set off depends upon the terms of
the contract and the facts.
The Judge found that the adjudicator in this case
had not come to any decision as to the total extension of time due
to Balfour Beatty. No specific entitlement to LADs logically
followed from the adjudicator's decision. Turning to the
contract, the Judge noted that the parties were required to give
effect forthwith to the adjudicator's decision. In the
circumstances, the Judge ordered Serco to pay the amount awarded by
the adjudicator, refusing permission to set off LADs. In the
circumstances the judge did not have to examine the validity of
Serco's withholding notice. The Judge also refused Serco's
application for a stay.
For full judgment, please click
here